Cancel a Disaster Recovery Plan Execution
You can cancel a Disaster Recovery (DR) plan execution to stop executing the plan. You cannot resume or retry a canceled DR plan execution.
Note
Canceling in-progress plan executions can leave the components in the application stack in an inconsistent state. You may need to manually recover individual components in the application stack after you cancel a plan execution.
Canceling in-progress plan executions can leave the components in the application stack in an inconsistent state. You may need to manually recover individual components in the application stack after you cancel a plan execution.
A DR protection group in a Needs attention state indicates that user intervention is required to resolve any underlying inconsistencies in the DR topology that may exist because DR plan execution was canceled. The DR Protection Group can be moved back to an Active state using the following steps:
- Navigate to the Resource page for the standby DR protection group.
- Click the More Actions menu and select Reset State to reset the DR Protection Group's state back to Active.
Note
This state reset must be performed separately for each DR Protection Group in a pair of associated DR Protection Groups.
Parent topic: Manage Disaster Recovery Plan Executions